 Corporate Profile: Nemaska Lithium Inc
    Publisher: Kaiser Research Online
    Author: Copyright 2013 John A. Kaiser

 
Nemaska Lithium Inc (NMX-T)
Trade DateVolumeHighLowCloseChgStatus
October 16, 20200$0.17$0.17$0.17$0.00Trading
KRO Profile - Members OnlyCorporate Web Site Not AvailableTreeExchQuote
Issued
84,764,338
Price
$0.165
Working Capital
($106,458,000)
Key People: Guy Bourassa (CEO), Robert Beaulieu (VP OP), Daniel Dufort (VP OP)
Diluted
119,629,322
Insiders
32.0%
As of
12/31/2019
Company supplied Corporate Overview - not available
The free corporate profile serves as a fast gateway for KRO members via the map cards to resources such as the KRO Profile which includes financial, insider and project details as well as news releases and KRO comments for which headline links are provided below. Links to the company's web site and project web pages are available within this free corporate profile if the company has a multi-user corporate membership (they are always available in full member only KRO Profile). A corporate membership provides the company with complete multiple user access to KRO resources and entitles the company to provide a corporate overview for the subject company's unrestricted corporate profile.

Active Project List
ProjectCountryState/ProvRegionNet
Interest
StageIPV $
MM
Target MetalsDeposit StyleTSC
(Project Name has a link to its location in the Members only KRO Profile)
WhabouchiCanadaQuebecJames Bay100% WI8-Construction $20Lithium BerylliumPegmatite
Company Project Gateway
Whabouchi Project
Company Project Web Page - N/A Canada - Quebec 100% WI8-Construction Lithium BerylliumPegmatite
Company News Releases - Members Only
Oct 15, 2020Granted Court Approval of the Sale Proposal from Orion Mine Finance, Investissement Quebec and The Pallinghurst Group
Aug 24, 2020Accepts a Sale Proposal from Orion Mine Finance, Investissement Quebec and The Pallinghurst Group
May 15, 2020Sells Its 15,849,455 Common Shares of Monarques
Jan 29, 2020Progresses In Restructuring Efforts Under CCAA
Jan 27, 2020Workforce Reduction
Jan 20, 2020Changes to Board of Directors
Jan 8, 2020Trader Note Delisting Review
Dec 24, 2019Bulletin 2019 0965: Delisting Review
Dec 24, 2019Trader Note Delisting Review
Dec 23, 2019Files for Creditor Protection Under the Companies' Creditors Arrangement Act
Dec 5, 2019Court Order For Interim Distribution Of Nominal Amount Of USD 350M Senior Secured Bonds
Nov 15, 2019Provides Update on Whabouchi Project
Oct 15, 2019Provides Update on the Whabouchi Project
Sep 17, 2019Court Application for the Discharge of Security Securing the USD 350M Senior Secured Bonds
Jul 19, 2019CAD 600M Equity Investment Proposal from The Pallinghurst Group
Jun 14, 2019Jumia Technologies AG (JMIA), Floor & Decor Holdings, Inc. (FND) & Livent Corporation (LTHM) Bronstein, Gewirtz & Grossman, LLC Reminds Investors of Class Actions
Jun 3, 2019Reminds Investors of Deadline in Securities Class Action Lawsuit Against Livent Corporation LTHM
May 16, 2019Provides Project Update
Apr 29, 2019Receives Independent Audit Report From BBA
Mar 28, 2019And Johnson Matthey Expand Lithium Hydroxide Supply Agreement
Mar 25, 2019Provides Update On Whabouchi Project Deployment Plan
Mar 12, 2019Welcomes New Directors
Feb 28, 2019Sends Lithium Hydroxide Monohydrate Samples to Several Potential Customers
Feb 19, 2019Terminates FMC (Livent) Supply Agreement
Feb 13, 2019Update on Overall Whabouchi Project
Jan 31, 2019To Resume Construction of Whabouchi Mine Site on February 5, 2019
Jan 31, 2019Fire At The Nemiscau Workcamp Cafeteria: Nemaska Lithium Provides Update
Jan 18, 2019Appoints Robert Beaulieu as Vice President, Operations
Dec 12, 2018To Hold Annual General And Special Meeting Of Shareholders
Nov 19, 2018Provides Project Construction Update
Nov 14, 2018CEO To Speak At The Deutsche Bank 2018 Lithium & Energy Storage Conference
Nov 7, 2018Vision Lithium Reports 1.85% Li2o over 13.50 Metres from Channel Sampling at the Sirmac Lithium Property
Oct 17, 2018CEO of Nemaska Lithium Inc Joins Uptick Newswire's Stock Day Podcast with an Update on Their Major Projects
Oct 16, 2018Removed from BCSC Delinquent Filer List - 2018/10/03 AIF Filings
Oct 11, 2018Partial Removal from OSC Delinquent Filer List
Oct 9, 2018BCSC Delinquent Filer 6 Days; Annual Information Form
Oct 8, 2018BCSC Delinquent Filer 5 Days; Annual Information Form
Oct 5, 2018OSC Delinquent Filer; Annual Information Form
Oct 1, 2018Provides Project Construction Update
Aug 29, 2018Confirms Fulfillment of Conditions Precedent to the Long Stop Date Under Its USD 350M Bond Offering
Aug 29, 2018CEO Guy Bourassa Visits Uptick Newswire's 'Stock Day' Podcast With Everett Jolly
Aug 23, 2018Receives First USD 75M Payment From Orion Under Streaming Agreement
Aug 20, 2018Finalizes a 5 Year Supply Agreement With Northvolt
Jul 23, 2018Provides Project Update
Jul 3, 2018LG Chem And Nemaska Lithium Announce Signature Of An Initial 5 Year Supply Agreement For Lithium Hydroxide
Jun 1, 2018Welcomes New Directors
May 30, 2018Completes Its CAD 1.1 Billion Financing Package
May 29, 2018Signs Supply Agreement for Spodumene Concentrate
May 28, 2018Bulletin 2018 0418: Additional Listing
May 22, 2018Halted Security
May 22, 2018C$280,000,000 Bought Deal Public Offering of Common Shares and C$80,000,000 Contemporaneous Private Placement of Common Shares
May 10, 2018Pricing and Closing of Books on USD 350M Bond Offering
Apr 27, 2018And Northvolt Announce Signature Of Agreement In Principle For Supply Of Lithium Hydroxide
Apr 25, 2018Launches A Usd 300 350m Bond Offering
Apr 25, 2018Cameo Neighbour Nemaska Lithium Announces Closing of $99 Million Subscription Receipt Financing With Softbank Group
Apr 25, 2018Closing Of Subscription Receipt Financing With Softbank Group
Apr 24, 2018Neighbor Nemaska Launches USD 300 350M Bond Offering
Apr 20, 2018Launches A USD 300 350m Bond Offering
Apr 12, 2018Concludes A USD 150m Streaming Agreement With Orion
Apr 6, 2018Softbank Group To Make Strategic Investment In Nemaska Lithium
Mar 28, 2018Advances In Lithium Project Financing Endeavors
Feb 20, 2018Shareholder Meeting Voting Results
Feb 16, 2018The Evolution of Electric Vehicles to Super Trucks
Feb 2, 2018Nemaska Announces the Completion Of The Sale Of Sirmac Lithium Property To ABE Resources And The Filing Of Early Warning Report
Jan 25, 2018Named To 2018 OTCQX Best 50
Jan 9, 2018Releases 2018 Feasibility Study
Jan 8, 2018Delivers Second Shipment Of Battery Grade Lithium Hydroxide From Whabouchi Concentrate And Releases Product Purity Specifications
Dec 22, 2017The Date And Place Of The Annual General And Special Meeting Of Shareholders
Dec 19, 2017Makes Reclamation Bond Installment For Whabouchi Mine And Announces Exercise Of Warrant And Options
Dec 14, 2017Signs Deal For Sale Of Sirmac Property To Abe Resources And Receives Mining Lease For Whabouchi Lithium Mine
Dec 4, 2017Confirms First Delivery Of Battery Grade Lithium Hydroxide From Whabouchi Mine Concentrate
Nov 14, 2017Massive Demand for Lithium Surges With Steady Growth in Electric Vehicles
Nov 9, 2017Power Grids Using Lithium ion as the New Power Storage Source Help Hike Demand
Nov 2, 2017Processes Lithium Sulfate Derived From Its Whabouchi Mine Concentrate Through Its Phase 1 Plant
Oct 10, 2017Processes Whabouchi Concentrate At The Phase 1 Plant And Provides Project Financing Update
Oct 9, 2017Removed from BCSC Delinquent Filer List - 2017/10/02 AIF Filings
Oct 5, 2017BCSC Delinquent Filer 3 Days; Annual Information Form
Sep 14, 2017Added To S&P/TSX Canadian Indices
Aug 14, 2017Brings In A Positive Recount Of Its Summer Activities At The Whabouchi Mine And The Shawinigan Plant, And Announces Changes To Organizational Structure
Aug 1, 2017Drill Results From Doris Zone And Infill Drilling
Jul 26, 2017Receives Final Milestone Payment From Johnson Matthey Following Approval Of Battery Grade Lithium Hydroxide From Phase 1 Plant
Jun 29, 2017Completes A $50 Million Bought Deal Public Offering
Jun 27, 2017Bulletin 2017 0613: Additional Listing
Jun 22, 2017Receipt For Final Short Form Prospectus
Jun 20, 2017Delivers Battery Grade Lithium Hydroxide To Johnson Matthey And Provides Phase 1 Plant Update
Jun 12, 2017Bought Deal Public Offering Of Common Shares And Provides Project Update
Jun 12, 2017Halted Security
May 18, 2017Receives New Patents Or Allowances In Canada, Australia And United States
May 5, 2017Johnson Matthey Battery Materials Approves Lithium Hydroxide From Nemaska Lithium And Releases $2m Milestone Payment
May 3, 2017Update On Whabouchi Mine Site And Phase 1 Plant
Apr 17, 2017Ready To Deliver First Tonne Of Lithium Hydroxide From Phase 1 Plant To A Customer
Apr 4, 2017Update On Lithium Concentrate Production And Phase 1 Plant Commissioning
Mar 22, 2017FMC Corporation Makes A Us$10m Payment Per Lithium Carbonate Supply Agreement
Mar 14, 2017Produces Up To 6.65% Li2o Concentrate From Dms Modular Mill At Whabouchi
Feb 13, 2017Achieves Phase 1 Plant Milestone And Triggers $3m Installment Payment From Johnson Matthey Battery Materials
Feb 8, 2017Successfully Commissions The Electrolysis Cell At Its Phase 1 Plant
Feb 2, 2017Named To 2017 Otcqx Best 50 Ranks No. 9
Jan 17, 2017Pursues Drilling To Further Define The Doris Zone
Jan 11, 2017Receives Australian Patent For Lithium Hydroxide And Carbonate Production
Dec 14, 2016Shareholder Meeting Voting Results
Dec 12, 2016Provides Progress Report On Mine Site And Phase 1 Plant
Dec 6, 2016Added To Solactive Global Lithium Index And Global X Lithium ETF
Dec 1, 2016Mineral Resource At Whabouchi
Nov 29, 2016Receives United States And Canadian Patents For Its Lithium Hydroxide And Lithium Carbonate Processes
Nov 28, 2016Drill Results From Doris Lithium Discovery
Oct 31, 2016FMC Corporation And Nemaska Lithium Sign Long Term Lithium Carbonate Supply Agreement
Oct 13, 2016Drill Results To Date On Whabouchi Lithium Project
Oct 12, 2016To Open Toronto Stock Exchange October 13, 2016
Oct 6, 2016Project Shaping Up On Time And On Budget
Sep 8, 2016Alchemist Mining Options Lithium Property Adjacent to Nemaska Lithium's Whabouchi Property
Sep 6, 2016Discovers New Mineralized Zone At Whabouchi And Provides Drilling Update
Aug 16, 2016Preps Whabouchi Mine Site For 60,000 T Bulk Sample And Modular Mill Installation
Jul 29, 2016Durango To Commence Nemaska Area Work Program
Jul 28, 2016Drilling Program At Whabouchi Lithium Project Progressing Well
Jul 13, 2016Begins A Targeted Definition Drilling Campaign On The Whabouchi Project With The Objective To Increase The Existing Lithium Resource And Extend The Mine Life
Jul 12, 2016Hires VP Operations To Oversee The Development And Operation Of The Whabouchi Lithium Mine And Hydromet Plant
Jul 8, 2016Completes $69 Million Financing And Commences Trading On The Toronto Stock Exchange
Jul 7, 2016Graduation, Delisting
Jul 6, 2016Bulletin 2016 0690: Original Listing
Jul 4, 2016Receipt For Final Short Form Prospectus
Jul 4, 2016Resume Trading
Jun 30, 2016Terms Of Offering
Jun 29, 2016Receives Second Installment Of $2.12 Million From Sustainable Development Technology Canada For Phase 1 Lithium Hydroxide Plant
Jun 28, 2016Private Placement Non Brokered
Jun 23, 2016Completes Initial MAG and VLF Survey at Whabouchi South Project Adjoining Nemaska Lithium?s Whabouchi Project in Quebec
Jun 23, 2016Durango Engages Theberge To Oversee Nemaska Whabouchi Area Claims
Jun 15, 2016Conditionally Approved For TSX Listing Its Shares
Jun 14, 2016Achieves Milestone For Ressources Quebec Cdn$5m And Jmbm Cdn$6m Payment Installments For Phase 1 Plant
Jun 10, 2016Financing By Way Of Short Form Prospectus
Jun 9, 2016Refiles Feasibility Study To Reflect Minor Oversights
Jun 1, 2016Receives Canadian Patent For Its Lithium Hydroxide And Lithium Carbonate Process And A Notice Of Allowance For The Corresponding Patent Application In The United States
May 24, 2016Receives First $5m Tranche From Ressources Quebec Inc. For Phase 1 Lithium Hydroxide Plant
May 20, 2016Update on Nemaska Properties
May 11, 2016Property Asset or Share Purchase Agreement
May 11, 2016Johnson Matthey Battery Materials Sign Definitive Agreement For The $12m Up front Payment For The Phase 1 Plant And Signs Commercial Offtake Agreement For Lithium Salts
May 10, 2016Completes Acquisition Of Shawinigan Facilities, Quebec
Apr 14, 2016Durango Adds Additional Pegmatite Ground And Negotiates On Additional Ground Adjacent To Nemaska's Whabouchi Property
Apr 7, 2016Durango Resources Announces: Historic Report Outlines Pegmatite On Durango Ground Adjacent To Nemaska's Whabouchi Property
Apr 4, 2016Whabouchi Updated Feasibility Study Shows A Pre tax Npv At 8% Discount Rate Of $1.9 B (after tax $1.16 B) And A Pre tax Irr Of 37.7% (after tax 30.3%)
Mar 28, 2016Confirms Closing Of A $13,000,000 Private Placement
Mar 24, 2016Confirms Closing Of A $13,000,000 Private Placement
Mar 11, 2016Presents At 28th Annual Roth Capital Conference On March 16, 2016
Feb 25, 2016Ranks As No. 2 Mining Company On Tsx Venture 50(r)
Feb 17, 2016Tops 2016 OTCQX Best 50
Feb 2, 2016Provides Update On Phase 1 Lithium Hydroxide Plant Construction Schedule
Feb 2, 2016Receives First Installment Of $2.1 Million From Sustainable Development Technology Canada For Phase 1 Lithium Hydroxide Plant
Jan 29, 2016Durango Resources Receives Unsolicited JV Proposal
Dec 24, 2015Grant Of Stock Options To Directors, Officers And Consultant
Dec 1, 2015Receives DTC Eligibility
Nov 23, 2015Appoints Francois Biron To Board Of Directors
Nov 19, 2015Resume Trading
Nov 19, 2015Signs Mou With Johnson Matthey Battery Materials To Collaborate On Phase 1 Plant
Nov 18, 2015Halt
Oct 19, 2015Receives Notice Of Allowance For Its Lithium Hydroxide And Lithium Carbonate Process Patent
Oct 6, 2015Intended Facilities Not Impacted By Fire In Shawinigan
Sep 10, 2015To Speak At Benchmark Intelligence Battery Raw Materials & Supply Chain 20/20 World Tour 2015
Sep 8, 2015To Build Hydromet Plant In Shawinigan, Quebec
Sep 4, 2015Receives General Certificate Of Authorization For Whabouchi Lithium Mine In Quebec
Aug 12, 2015Provides Update On Community Relations For Its Whabouchi Mine Project
Aug 4, 2015Warrant Term Extension, Warrant Price Amendment, Amendment
Jul 30, 2015Receives Positive Federal Environmental Assessment Decision For Whabouchi Project
Jul 15, 2015Private Placement Non Brokered
Jul 9, 2015Enhances And Expands Team
Jun 8, 2015Discusses Future Demand For Lithium Hydroxide
Apr 2, 2015Completes Comex Public Hearings For Whabouchi
Mar 16, 2015Prospectus Share Offering
Mar 11, 2015Confirms Closing Of A $400,000 Private Placement
Feb 20, 2015The Closing Of The Maximum Offering Under Its Prospectus Supplement No. 5
Feb 17, 2015Mine Permitting Public Hearings For Whabouchi
Feb 17, 2015Secures $12.87 Million Grant From Sustainable Development Technology Canada For Phase 1 Lithium Hydroxide Plant
Feb 4, 2015Confirms Closing Of The Minimum Offering Of $1m Under Its Prospectus Supplement No. 5
Jan 6, 2015Private Placement Brokered, Correction
Dec 31, 2014Prospectus Share Offering, Correction
Dec 22, 2014Provides Permitting Update On The Whabouchi Lithium Project
Dec 12, 2014Private Placement Brokered
Dec 12, 2014Prospectus Share Offering
Nov 17, 2014Financing Oversubscribed At $1,542,500
Nov 14, 2014Closes $1,250,000 Financing And Invites Shareholders To AGM
Nov 7, 2014Social Economic Partnership Agreement For The Whabouchi Mine Signed Between Cree Parties And Nemaska Lithium
Nov 5, 2014To Sign Impact Benefit Agreement With The Crees
Aug 27, 2014Patent Applications Published
Jul 16, 2014Issues 500,000 Common Shares For The Whabouchi Property
Jul 2, 2014Files Whabouchi Feasibility Study And Continues Strategic Discussions
May 13, 2014Media Advisory: Nemaska Lithium To Review Feasibility Study Results
May 13, 2014Whabouchi Feasibility Study Shows Npv Of $924m And Irr Of 25.2%
May 5, 2014Advances Environmental Permitting On Whabouchi
Apr 30, 2014Prospectus Share Offering
Apr 15, 2014Closing Of Over Allotment Option
Apr 10, 2014Confirms 99.99% Lithium Hydroxide From 1,000 Hour Test And Confirms Operating And Capital Expenditures For Feasibility Study
Apr 2, 2014Closes $3,250,000 Financing
Mar 20, 2014Resume Trading
Mar 19, 2014Revises Terms Of Its $5,000,000 Public Offering
Mar 13, 2014The Filing Of A Third Prospectus Supplement For A Minimum Offering Of $3,500,000 And A Maximum Offering Of $5,000,000
Jan 28, 2014Increases Mineral Resource At Whabouchi
Dec 11, 2013Recovery Rate By 16.7% From Its Dms Circuit: Implications Are Significant Savings In Capital And Operation Expenditures
Nov 21, 2013Prospectus Unit Offering
Nov 14, 2013The Completion Of The Maximum Of The Offering
Nov 13, 2013Intersects 2.19% Li2o Over 10.04 M And Extends The Main Zone By 200 Meters At Whabouchi
Nov 11, 2013A C$2,200,443.92 Final Closing Offering
Oct 28, 2013A C$2,000,444 Closing
Oct 17, 2013The Filing Of A Second Prospectus Supplement For A Maximum Offering Of $2,500,000
Oct 3, 2013Whabouchi Mining Project Public Comments Invited
Oct 1, 2013Correction From Source: Nemaska Lithium Extends Mineralization To
Oct 1, 2013Extends Mineralization To The East Of Its Whabouchi Deposit
Sep 4, 2013Provides Update On Whabouchi Lithium Mine And Processing Plant

 
 